Jobs, visits and projects
How Homeforce organizes work - a job holds one or more visits, and a project is a job with phases, a budget and change orders.
Everything your crew does for a customer lives on a job. Knowing how jobs, visits and projects fit together makes the rest of Homeforce click.
A job is the work
A job is one piece of work for one customer at one address, like "AC not cooling upstairs" or "Exterior repaint". It has a number (Job #1042), a job type, a priority and a status. Estimates, invoices, notes, photos and costs all hang off the job.
A visit is a trip
A visit is one trip to the job: a date, a time, and who's going. A job can have as many visits as it needs:
- A repair with a parts run: a diagnosis visit, then a return visit.
- A two-day install: one visit per day.
- A job nobody has scheduled yet: one visit with no time, waiting in Unscheduled on the dispatch board.
Visits are what show up on the dispatch board, the Schedule page and your techs' phones. Each has its own status (Scheduled, En Route, On Site, Completed), and the job's status follows from them. See Visit statuses.
A project is a bigger job
A project is a job with extra tools for work that runs over days or weeks:
- Phases with start and end dates, shown on a Gantt chart
- A contract amount and cost budget, with budget vs actual
- Change orders the customer signs
- Daily logs, a punch list and a photo timeline
- Progress billing by percent complete
A project still has visits. You can tie each visit to a phase.
| Service job | Project | |
|---|---|---|
| Typical length | Hours, one or a few visits | Days to weeks |
| Scheduled as | Visits on the dispatch board, or crew days | Visits and crew days, grouped into phases |
| Billed | Invoice when done, or a deposit first | Deposits and progress invoices |
| Extra tabs | — | Phases, plus project costs on Costs |
Which one you get
When you create a job, pick Service call or Project. Picking a job type picks for you: types set up as Project with phases in Settings → Job types & modes create projects; service calls and multi-day crew jobs create service jobs.
Turn a job into a project
Sometimes a service call turns into something bigger. On the job, click Convert to project, enter the Contract amount, Cost budget and Target completion, and click Convert. Every visit, estimate, invoice, note and photo stays. Existing visits are grouped into a first phase called "Diagnosis & Service" (or "Phase 1" if there were no visits). There's no way to turn a project back into a service job.
Was this helpful?
Related articles
Jobs and projects
Create a job or project
Add a job or project for a new or existing customer, schedule its first visit or send it to the unscheduled queue.
Jobs and projects
Manage a project
Break a project into phases, see them on a Gantt schedule, update percent complete, tie visits to phases, and bill progress.
Scheduling and dispatch
Use the dispatch board
See every tech's day on one timeline, drag waiting work onto the board, and keep the day on track from the office.
Sales
Create an estimate
Start an estimate for a customer, add line items from your pricebook, and save it ready to present or send.
Still stuck?
Our team answers support emails during business hours, usually within a few hours.